Tutorial Step 15: Set the Baseline

When you have a schedule set up and leveled properly, and the project is ready to begin, choose Set Baseline from the Project menu. This copies the schedule you created into a baseline schedule. The baseline schedules remain unchanged as you update the actual schedule; as the project goes on you can keep track of how closely it is following the original plans.
You can choose Split or Both from the Baseline/Actual menu on the toolbar to compare the baseline schedule to the actual schedule.